Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 14, assuming the CPI remains the same through the remainder of the job.
The ACWP at the end of the second week for the project in Problem 12 is $37,900. Determine the CPI for the project.
A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week?
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Construction Accounting And Financial Management (4th Edition)
- Please use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: Box Springs estimates there will be four orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardPlease use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: It estimates there will be five orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardThe Larry plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance - P100,000; Inspection - P150,000. The plant currently applies overhead using direct labor hours and expected capacity of 50,000 direct labor hours. The following data have been assembled for use in developing a bid for a proposed job: (refer to image) Total expected machine hours for all jobs during the year is 25,000, and the total expected number of inspections is 1,500.Using activity-based costing and the appropriate activity drivers, the total cost of the potential job would be * Nimet malerials Direcd lubor Mechine houre Number of inspections Niret labor hours P1 C00 P4.000 600 800 O a. P2,400 О Б. Р3,600 c. P7,400 O d. P7,750arrow_forward
- A work element takes 20 hours of labor of a technician. Currently, the technician makes $22.50 per hour. For this project, the overhead charges are 72% of the direct labor charges and 10% personal time was assumed for this work element. a. What would be total direct labor cost to complete the work element? b. What would be the total overhead cost to complete the work element? c. What would be the total personal time cost to complete the work element?arrow_forwardWhite Consulting, a real estate consulting firm, specializes in advising companies on potential new plant sites. The firm uses a job cost system with a predetermined indirect cost allocation rate computed as a percentage of expected direct labor costs. At the beginning of the year, managing partner Kenna White prepared the following plan, or budget, for the year: Direct labor hours (professionals). . . . 16,000 hours Direct labor costs (professionals). . . . $2,350,000 Office rent. . . . . . . . . . . . . . . . . . . . . . $220,000 Support staff salaries. . . . . . . . . . . . . $940,000 Utilities. . . . . . . . . . . . . . . . . . . . . . . . $350,000 Tibbs Resources is inviting several consulting firms to bid for work. White estimates that this job will require about 200 direct labor hours. Requirements: 1. Compute WhiteConsulting's (a) hourly direct labor cost rate and (b) indirect cost allocation rate. 2. Compute the…arrow_forwardA work element takes 20 hours of labor of a technician. Currently, the technician makes $22.50 per hour. For this project, the overhead charges are 72% of the direct labor charges and 10% personal time was assumed for this work element. What is the grand total cost to complete this work element? (the total be the sum of the direct labor, overhead, and personal time cost)?arrow_forward
- Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $40,000, design $300,000, and construction oversight $100,000. The cost drivers and expected use are as follows.Expected Use of Cost Drivers Activities Cost Drivers per ActivityInitial concept formation Number of project changes 20 Design Squarefeet 150,000 Construction oversight Number of months 100(a) Compute the predetermined overhead rate for each activity. (b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.arrow_forwardCalculate the direct and total direct costs of labor for a project team member using the following data: Hourly rate: $50/hr Hours needed: 100 Overhead rate: 30%arrow_forwardThe management of Red Star Company estimates that 60,000 machine-hours will be required to support the production planned for the year. It also estimates $300,000 of total fixed manufacturing overhead cost for the coming year and $5 of variable manufacturing overhead cost per machine-hour. What is the predetermined overhead rate?arrow_forward
- cS Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below: Estimated Costs to Complete Site Contract Cost Billings on Collections on Price Incurred Contract Billings 5,000,000 3,750,000 5,000,000 5,000,000 2 7,000,000 1,000,000 4,000,000 900,000 900,000 3 2,500,000 1,000,000 1,000,000 1,500,000 1,000,000 If the company records revenue over time, how much must be shown as current asset in the balance sheet of MOC Construction Company as of December 31? A. 5,500,000 B. 500,000 C. 250,000 D. 100,000arrow_forwardCS Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below: Site Contract Cost Estimated Costs Billings on Collections on Price Incurred to Complete Contract Billings 5,000,000 1 5,000,000 3,750,000 5,000,000 2 7,000,000 1,000,000 4,000,000 1,000,000 900,000 1,500,000 900,000 1,000,000 3 2,500,000 1,000,000 If the company records revenue at a point in time, how much must be shown as current asset in the balance sheet of MOC Construction Company as of December 31? A. 5,100,000 B. 500,000 C. 250,000 D. 100,000arrow_forwardAaron Company estimates direct labor costs and manufacturing overhead costs for the coming year to be $800,000 and $500,000, respectively. Aaron allocates overhead costs based on machine hours. The estimated total labor hours and machine hours for the coming year are 16,000 hours and 10,000 hours, respectively. What is the predetermined overhead allocation rate? A) $80.00 per machine hour B) $31.25 per labor hour C) $81.25 per labor hour D) $50.00 per machine hourarrow_forward
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College