Interpretation:Company that would be awarded the contract if categories of quality and price are given
Concept introduction: Bidding is the process used to select the contractor who would do the required work at lowest price. It is the simplest procedure where the cost is calculated and the lowest responsive price is selected to get the work done.
Explanation of Solution
The procurement department of H hotels is evaluating tenders for its newest hotel resort. Four tenders have been received and tender is being evaluated based on quality and price. Quality is being quantized on a
Bid prices are converted based on a
Details of bids are as follows:
So total price for bid would be:
So total price for bid would be:
So total price for bid would be:
So total price for bid would be:
Lowest offer price is from UCcosting
Company | Bid price | Difference in bid price with lowest bid price | Price score | Quality score |
OR LLC | ||||
WC | ||||
UC | ||||
DC |
Now price is given weightage of
Thus weighted score of tender would be:
Company | Price score | Quality score | Weighted average score |
OR LLC | |||
WC | |||
UC | |||
DC |
Under linear averaging method score of each tender will be result of sum of individual score in each category multiplied by corresponding category weight.
DC should be awarded the contract under average weighted linear cost method as it has the highest average weighted score.
Want to see more full solutions like this?
Chapter 9 Solutions
Practical Operations Management
- a strategy in which the company charges the same price plus freight to all customers, regardless of their location is related to: Select one: a. Freight-absorption pricing b. Zone pricing c.Uniform-delivered pricing d. FOB pricingarrow_forwardWhat are the factors that affect Options contracts? Which is the most and least significant of the factors?arrow_forwardOne of your Taiwanese suppliers has bid on a new line of molded plastic parts that is currently being assembled at your plant. The supplier has bid $0.10 per part, given a forecast you provided of 300,000 parts in year 1; 500,000 in year 2; and 700,000 in year 3. Shipping and handling of parts from the supplier's factory is estimated at $0.03 per unit. Additional inventory handling charges should amount to $0.004 per unit. Finally, administrative costs are estimated at $20 per month. Although your plant is able to continue producing the part, the plant would need to invest in another molding machine, which would cost $10,000. Direct materials can be purchased for $0.04 per unit. Direct labor is estimated at $0.05 per unit for wages plus a 50 percent surcharge for benefits and, indirect labor is estimated at $0.013 per unit plus 50 percent benefits. Up-front engineering and design costs will amount to $40,000. Finally, management has insisted that overhead be allocated if the parts are…arrow_forward
- You have been asked to bid for the potential outsourcing of the Facilities Management operations of Kings Avenue Mall, in Paphos. Draft an outline of what you consider to be the THREE most significant. components of a service level agreement to cover the main facilities management operations to be outsourced. Ensure that you include specific service level deliverables that can be measured and the consequences of non-performance.arrow_forwardOne of your Taiwanese suppliers has bid on a new line of molded plastic parts that is currently being assembled at your plant. The supplier has bid $0.10 per part, given a forecast you provided of 200,000 parts in year 1; 300,000 in year 2; and 500,000 in year 3. Shipping and handling of parts from the supplier’s factory is estimated at $0.01 per unit. Additional inventory handling charges should amount to $0.005 per unit. Finally, administrative costs are estimated at $20 per month. Although your plant is able to continue producing the part, the plant would need to invest in another molding machine, which would cost $10,000. Direct materials can be purchased for $0.05 per unit. Direct labor is estimated at $0.03 per unit plus a 50 percent surcharge for benefits; indirect labor is estimated at $0.011 per unit plus 50 percent benefits. Up-front engineering and design costs will amount to $30,000. Finally, management has insisted that overhead be allocated if the parts are made in-house…arrow_forwardList the disadvantages (min 5 points) of traditional procurement approach and see what are the methods or strategies to improve the system by having other forms of procurement systems. Explain the pros and cons of the selected tender method in a table form and how this method may be enhanced.arrow_forward
- General Transfer Pricing Rule; Goal Congruence American Motors Inc. is divided, for performance evaluation purposes, into several divisions. The Automobile Division of American Motorspurchases most of its transmission systems from another unit of the company. The TransmissionDivision’s incremental cost for manufacturing a standard transmission is approximately $1,350 perunit. This division is currently working at 75% of capacity. The current market price for a standardtransmission is approximately $1,875.Required1. Using the general transfer pricing rule presented in the chapter, what is the minimum price at which theTransmission Division would sell its output to the Automobile Division?a. $1,013b. $1,350c. $1,613d. $1,875arrow_forwardMo a) Explain how you would obtain pricing from UKEP, given that you are an established distributor. b) Your eText identifies several types of discounts that suppliers are prepared to offer. Identify and describe them. Which discounts might be applicable to you c) Assuming 3 employees in your Purchasing department, prepare a Table with reasonable estimates of the activity costs of placing an order with UKEP ?arrow_forwardBriefly discuss the following Are Costco’s prices too low? Why or why not?arrow_forward
- Mr. Williams, the leather handbag buyer for an upscale menswear specialty retailer located in San Francisco, decides to review his vendor analysis report before making his forthcoming season’s purchases. The report shows that there are three relatively strong and three relatively weak suppliers among the top six resources in relation to the gross margin each generated. Mr.Williams realizes that some important aspects of his job as a buyer are to negotiate trade discounts, quantity discounts, cash discounts, dating, and transportation charges. Because any and/or all of these factors can increase the essential gross margin figure, he examines copies of past orders to determine the terms of sale on previous purchases. He discovers that some suppliers granted all his requests pertaining to discount and dating elements, certain vendors negotiated these factors only after an initial order was placed, and a considerable number allowed only the absolute minimum discount that prevailed in the…arrow_forwardAmy Lloyd is interested in leasing a new car and has contacted three automobile dealers for pricing information. Each dealer offered Amy a closed-end 36 month lease with no down payment due at the time of signing. Each lease includes a monthly charge and a mileage allowance. Additional miles receive a surcharge on a per-mile basis. The monthly lease cost, the mileage allowance, and the cost for additional miles follow: Monthly Cost Mileage Allowance Cost per Additional Mile Dealer Dealer A $309 36,000 $0.15 Dealer B $320 45,000 $0.20 Dealer C $335 54,000 $0.15 Amy decided to choose the lease option that will minimize her total 36-month cost. The difficulty is that Amy is not sure how many miles she will drive over the next three years. For purposes of this decision she believes it is reasonable to assume that she will drive 12,000 miles per year, 15,000 miles per year, or 18,000 miles per year. With this assumption Amy estimated her total costs for the three lease options. For example,…arrow_forwardYour firm received an RFP (request for proposal) on a wire harness from GM with fixed costs of $1 million and MC of $1 with expected sales of 1 million units. What is break-even price?arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning