1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION 4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS 5. WHEN WILL THE PROJECT BE COMPLETED?
Q: Required to prepare the action plan for the events show in table below and determine the Total Float…
A: Based on the Predecessor relationships given (the 2nd column of the tables show the predecessors of…
Q: a. Develop a network representation of this problem. b. Develop a linear programming model that can…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Describe how an organization can use a social media site such as LinkedIn to hire the best people
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: What is value added, and how is it achieved? value adding is basically a simple process c
A: Here, I have answered the first question, as there are multiple different questions The value…
Q: In the business, total quality management is a management approach focusing on quality. Considering…
A: Total Quality Management is a management strategy based on the premise that all workers continually…
Q: A procedure in one of the company's functional areas is now being developed using Internet…
A: E-Business permits organizations to interface their inside and outer cycles all the more…
Q: What is project planning? Examine the significance of project planning. Outline the activities…
A: Project planning is the process of developing and maintaining an organized approach to the…
Q: This large business has 127 employees, 19 of whom are managers or supervisors; its reduced…
A: Productivity is the relationship between the volume of the input and output that is calculated in…
Q: Compilation of at least three trend in quantity food production.
A: Quality food production has become an important subject in recent years, with many social media…
Q: vaccine marketed by a drug company has a known and constant demand of 1,200 units per year or 100…
A: The question is related to the Inventory Management. The Optimum Quantity per batch with the help of…
Q: Differentiate between speculative and event risks.
A: Risk management can be stated as the approach of recognizing, evaluating, and handling or…
Q: In your own word, What level (micro, mezzo, macro) of social work do you see yourself practicing in?…
A: Although micro, mezzo, and macro social work are different sub-disciplines of social work, it is…
Q: The Center for Information Technology at State University has outgrown its office in Bates (B) Hall…
A: The probability calculation identify the chances of getting the target based on the consideration of…
Q: provides domestic and international air transport services. Explain the five services outputs…
A: At the beginning of Qatar Airways' existence, it was launched on November 22, 1993. With more than…
Q: You process four product types using four resources (Resource A, Resource B, Resource C and Resource…
A: Production management is described as the means and ways of managing the different business…
Q: A manager wants to determine an appropriate learning percentage for processing insurance claims for…
A: Given data: Repetition 1 2 3 4 5 6 Time (minutes) 50 46 43 38 37 34
Q: 14. Changes in the weather, pests, and diseases make it difficult for farmers to supply the amount…
A: Contract farming is an agreement between a farmer and a buyer. In contract farming the buyer states…
Q: EXPLAIN the following LEGAL ISSUES in terms of Gender Preference in WORKPLACE
A: Gender preference is seen globally in many workplaces. Men and women are treated differently in the…
Q: Discuss the meaning of the term downstream effect in risk management.
A: Risk management is the recognition, assessment, & prioritization of risks trailed by coordinated…
Q: a) RDL Corporation has one small plant located on the outskirts of Manila. production is limited to…
A: Let a be number of alpha products produced Let b be number of beta products produced Unit…
Q: Amber Pvt Ltd sells 240,000 stools per year. Based on the company's policy, a safety stock of 4…
A: Inventory management is done to maintain enough stocks so as to avoid wastage.
Q: What is the most significant contrast that can be drawn between the agile technique of project…
A: Both agile techniques and the waterfall method are two very different approaches that can be used…
Q: How many units of Item X should be ordered each time? O 94 units O 95 units 100 units O O
A: EOQ stands for economic order quantity. It is a company's optimal order quantity that undervalues…
Q: please answer quick in details within 30 mins.
A: Throughput is the number of units that can be produced by a production process within a certain…
Q: (2) In the context of project management, why is it important to manage risks?
A: Project management is a process that requires the management of resources, time, and money in order…
Q: Susan Solomon has been thinking about starting her own fuel station, but Susan's problem is to…
A: Given data:
Q: 1- Total project finishing time 2- Critical path 3- Free float for each task.
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Could you please explain the Service Process Structuring
A: The service process structuring is done as a part of the process strategy, the main objective is to…
Q: What is the purpose, usefulness, and limitation of Poter's 5 forces strategy?
A: Porter's five forces strategy is a business modeling strategy that determines the strengths and…
Q: le to those of Shorte
A: The priority scheduling algorithm performs the processes based on their priority. To ensure that…
Q: For the EOQ policy, the total annual stocking cost (the sum of the holding and ordering costs) for…
A: Inventory management is the process of planning, monitoring, and controlling the movement of…
Q: Calculate manpower needs A manufacturing company plans following production and labour intensity of…
A: In this question, For each product, we have Labor intensity and planned production units, from this…
Q: What elements in the external environment might
A: Pixar has been around since the early '80s and has released more than 15 feature films over the past…
Q: a) Draw the precedence diagram. b) What is the cycle time to meet a forecasted demand of 400 units…
A: First I would prepare the precedence Diagram, The table data includes Task id, time for each task…
Q: Detail the design principles as well as the overall concept of the design. What qualities must a…
A: Product design is an important factor in customer buying behavior and therefore it has some…
Q: Ethics and morality are synonymous, and both refers to customary behavior. A) True B) False
A: Customary can be stated as the approach of doing something according to the approved or confirmed…
Q: Minimum project completion time = weeks
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: What are the two systems of maintaining inventory? Briefly define each.
A: Inventory is the raw materials and finish products that are stored into the company's warehouse for…
Q: Reduces costs and their feasibility ranges are rooted in making changes in the right hand side of…
A: Feasibility ranges can be stated as the amount that will be interchanged in the objective function…
Q: How can 7R's of Supply Chain Management (SCM) can be a source of competitive advantage for a…
A: The seven R's of supply chain management are used as strategies to achieve business objectives and…
Q: Identify the critical path. (Write the letters without spaces and commas.) Determine the number of…
A: A slack value indicating the available time in each activity to adjust without affecting the project…
Q: three important professional workplace expectations. and What disciplinary action is appropriate…
A: Important professional workplace expectation: 1) correspondence 2) How could I should act? 3)…
Q: In the area of operations, what are some of the differences and similarities between high-contact…
A: Service operations deal with the infrastructure, processes, and activities that are associated with…
Q: Apply the product or service planning and development process. Follow this process from the idea,…
A: The product planning and development process is a product cycle that comprises different stages…
Q: Demand in each period is normally distributed with a mean of 100 and standard deviation of 50.…
A: Here, for each period, the demand data shows normally distributed with a mean value of 100 and a…
Q: Ql: For the project listed below, find the following items: 1- Total project finishing time. 2-…
A: As per our guidelines, we are supposed to answer only three sub-parts if multiples sub-parts are…
Q: Which of the following Metrics can be used as a KPI? (Select all that apply) a. Reliability O b.…
A: Operations key performance indicators are described as the items that can be measured by an…
Q: e of a business enterprise? a. all departments b. all activities in the firm c. all departments…
A: Operations structure of a business enterprise
Q: WhAt is Integer Linear Optimization and how it is solved?
A: Linear optimization is one of the most popular techniques in linear programming. ILO was first…
Q: c) Jay Calahi is to supply gravel for projects located in three different sites. He has three…
A: Given data is
Trending now
This is a popular solution!
Step by step
Solved in 6 steps with 10 images
- AutoSave Off Document1 - Word O Search retroget File Home Insert Draw Design Layout References Mailings Review View Help A Share P Comments P Find - E Replace Calibri (Body) - 11 - A A Aa- A AaBbCcDc AaBbCcDc AaBbC AaBbCcC AaB Paste I U - ab x, x A - I v A v E 1E- 1 Normal I No Spac. Heading 1 Heading 2 Dictate Editor Reuse В Title A Select v Files Clipboard Font Paragraph Styles Editing Voice Editor |Reuse Files а) Janadu IT Sdn Bhd is planning to build a new database farm. Table 2 displa activities for the project. Table 2 Activity Immediate, Predecessors Duration A 9 B C A 12 D A 5 E 6 F B 8 G C, F 3 H D 2 I H 8 J G, I K E, J Page 1 of 1 O words English (Malaysia) DFocus 100% 4:33 РM 33°C Rain A 4)) G 26/06/2021BSOP 588 Managing QualityAll Assignments Course Projects, Midterm and Final ExamWeek 2 Course Project:BSOP 588 Week 2 Project Proposal (Toyota Motor Corporation)Week 3 Assignments:Week 3 Paper; Measuring Customer Service – MCS (Jan 2013)Week 3 Paper; Measuring Customer Satisfaction (July 2014)Week 4 Midterm ExamSET 1Page 1Question (TCO A) Compare and contrast the evolution of quality and the role it played in the management of U.S. and Japanese business firms from the 1950s to the present.Question (TCO B) Compare and contrast the following definitions of quality. Definition 1: Quality is the totality of features and characteristics of a product or service that bears on its ability to satisfy given needs. Definition 2: Quality is meeting or exceeding customer expectations.Question (TCO A) Explain the three core principles of total quality.Question (TCO H) Identify and discuss five differences between service and manufacturing organizations.Question (TCO B) Cite two ways that the…1. How does a feasibility report differ from a justification report. 2. What is problem factoring.
- Microsoft Excel 16.0 Sensitivity Report Worksheet: [Book1]Sheet7 Report Created: 9/26/2020 10:43:05 AM Engine: Standard LP/Quadratic Objective Cell (Min) Cell Name Final Value $B$13 Obj Func AN 4135000 Decision Variable Cells Final Reduced Objective Allowable Allowable Cell Name Value Cost Coefficient Increase Decrease $B$11 variables AN 55000 0 33 7.0000001 41.0000001 $C$11 variables AO 0 7 48 1E+30 7 $D$11 variables BN 25000 0 27 8.0000001 7.0000001 $E$11 variables BO 47000 0 35 7.0000001 8.0000001 Constraints Final Shadow Constraint Allowable Allowable Cell Name Value Price R.H. Side Increase Decrease $B$16 LHS 55000 41 55000 10500 47000 $B$17 LHS 72000 35 72000 10500 47000 $B$18 LHS 80000 -8 80000 47000 10500 $B$19 LHS 47000 0 57500 1E+30 10500 The answers to the questions…4a) Total quality management is a top-down program True/ False 4b) The qualifications of a competent project manager are: technical expertise, related project experience, business capability, leadership ability, people skills and appropriate educational degree. True/ False 4c) A good method to ensure client satisfaction is to develop criteria and a related measurement program and periodic report that show the contractor's performance against the criteria. True/ False 4d) Some of the elements for an effective team-building program are: project commitment, cost and schedule consciousness, and working togetherness True/ False Make sure you solve all question, I need only answers. If you are going to solve please left this question. I need all answers.... **A O Standord Max Мaximize Р — 10х + 12y subject to x + 2y 0 Screen clipping taken: 11/23/2019 6:23 AM C Мaximize P 3 3х + 4у + 5z subject to x + y + z 0, z 20 Screen clipping taken: 11/23/2019 6:24 AM D Maximize P = 12x + 10y + 5z subject to 2х + у +zs 10 3x + 5y + z < 45 2x + 5y + z < 40 x 2 0, y 2 0, z 2 0 Screen clipping taken: 11/23/2019 6:25 AM
- 2. The following figure demonstrate the personnel involved in any project from sampling to data user. Discuss the hierarchy and role of each personnel. Project manager Sampling - Field personnel - Field engineer - Geologist Soil specialist Data user Lab analysis - Chemist Data analysis Statistician Client Decision maker QA/QC specialistMatch the following: 1. Reposition a product - 2. Marketing a product - 3. Scheduling production- 4. Modifying plant and equipment- 5. Raising money and paying debt- 6. Inventing a new product- A. Action steps include:Research the opportunity in the segment in the CourierSelect appropriate product attributes - Performance, Size, MTBFDisplay the R&D worksheet.Enter the product attributesNote the R&D completion dateDisplay the Production worksheetOrder capacity and automation (optionally, wait a year)Display the Finance worksheetFund the plant with stock and bond issuesSave the decisions B. Action steps include:Research the competitive environment in the CourierDisplay the Marketing worksheetEnter decisions for Price, Promotion and Sales BudgetsObserve the decision impact upon the computer's forecastDevelop a worst case estimate for demandEnter your worst case estimate for in the sales forecastSave the decisions C. Action steps include:Estimate peak demand…AutoSave Module 7 Excel Quiz Excel Search Sebastian Beltran 回 X Off SB File Home Insert Page Layout Formulas Data Review View Help A Share Comments Insert Calibri v 11 ab Delete Paste $ • % 9 58 28 Conditional Format as Cell Sort & Find & Ideas Sensitivity BI U A K0 .00 00 0 v Format Formatting v Table v Styles v Filter Select Clipboard Font Alignment Number Styles Cells Editing Ideas Sensitivity C23 fx A В C D E F G H K M Q R U 7 Perpetual Inventory Using FIFO 8 Beginning inventory, purchases,and sales data for Keurig coffee machines are as follows: 9. 10 June 1 Inventory 50 units at $10 11 6. Sale 20 units 12 14 Purchase 90 units at $11 13 19 Sale 60 units 14 25 Purchase 40 units at $13 15 30 Sale 50 units 16 17 The business maintains a perpetual inventory system, costing by the first-in, first-out method. 18 Using the chart below, determine the cost of ending inventory. 19 20 Sales Date Purchases Inventory 21 (Cost of goods) 22 Unit Cost Total Unit Cost Total Unit Cost Total 23 24…
- Let’s assume you are the new full time manager that the school has hired to take over running the wellness center and create 2 new programs to bring in more students/faculty to use the facilities. You need to create a proposal to give to the school on ways to improve the wellness center. What equipment is necessary to add to the wellness center? (AED, CPR certification for all employees?) What else would you want to add to the wellness center? How much would they cost? Please list out the costs ( ex: 3 treadmills: $ 3000/treadmill = $9000, Fresh towels: 25 towels at $3/each = $75) Use your imagination here. What would make the wellness center inviting? New Tvs? Towels? Better equipment? Music system? Outdoor classes that need equipment? You have to use the space you have but be creative! You have $25,000 ! Spend it! You will need to search for this information online. Please be sure to include references from where you found your costs. New Proposed Equipment: Item…1. Assume you work for an organization that intends to use process mining to examine several of its processes. The first process you are considering is hiring a new employee to work for your large company. To get started, you must a. List the activities that are likely to be recorded in a database related to hiring an employee. b. Brainstorm what types of analyses you could perform by looking at the activities and time stamps for thote activities. Suggest three analyses that you could perform if this data was collected and put into a process mining dashboard. As you consider the analyses, think about analyses that would be useful to internal and external auditors, the HR Department and other groups.All of the following terms have the same meaning EXCEPT: a cause and effect diagram b Ishikawa diagram c fishbone diagram d affinity diagram Costs for solutions are often ____________. a overestimated b underestimated c high d low