a. What is the expected completion time of the project? b. What is the probability of completing the project in 21 days or less? c. What is the probability of completing the project in 17 days or less?
Q: (d) Management realized that the optimal product mix, taking setup costs into account, might be…
A: The decision variables are already given. Objective function: Max…
Q: 1. Identify critical components of the procurement cycle
A: As per our guidelines, we are supposed to answer only first part if multiple parts are given.
Q: Boardwalk Electronics manufactures 250,000 circuit boards per month. A random sample of 7,000 boards…
A: Given data: Random sample size = 7,000 boards Defects in one characteristic = 4 defects Defects in…
Q: What is the BEST source of lighting for a web conference? O an uncovered window behind you O a soft…
A: Web conferences means meeting virtually using laptop or desktop with web cam on. Communication is…
Q: Discuss the purpose of employing business process modeling and notation in organizations, why it is…
A: By providing a data-driven visual presentation of the most important business processes, business…
Q: An appliance manufacturer wants to contract with a repair shop to handle authorized repairs In…
A: Process capability Ratio (Cpk) is a statistical tool which helps to identify the process capability…
Q: Johnson Electronics Corporation makes electric tubes. It is known that the standard deviation of the…
A: Given data: Mean (μ)= 2300 Standard deviation (σ) = 145 Sample size (n) =90
Q: Circuit Board Fabricators-Process Data Required output per shift Average job size (boards)…
A: Process Flow Structure: As per the given case, we conclude that the process flow…
Q: With reference to the case study, discuss the main reasons that have been influential in…
A: Operation management is performed in each manufacturing organization. It all deals with the…
Q: “Being successful in business requires a number of qualities and competencies, not all of which can…
A: The aptitude and preparedness to create, plan, and manage a business enterprise—along with all of…
Q: Expando, Inc., is considering the possibility of building an additional factory that would produce a…
A: This is a diagrammatic representation of decisions available to choose from considering the…
Q: Draw a simple bill-of-materials (BOM) for a smart phone given the following requirements: (a)…
A: The components in a bill of materials for a smartphone are listed below. Smartphone Components…
Q: Your firm received an RFP (request for proposal) on a wire harness from GM with fixed costs of $1…
A: A break-even price is the value change that just recovers one's initial cost or investment. The…
Q: 9- All of these are key areas of a typical spend analysis except a-Spend by division, department, or…
A: Spend Analysis is related to Strategic Planning and Execution. It is one of the processes carried…
Q: 4. A production manager at any is monitoring the quality of the company's production process. There…
A: Given data:
Q: Emerald manufactures large screen televisions. Their best-selling model has annual demand of…
A: Given data: Annual demand = 8,000 units/year Daily production capacity (p) = 200 units/day. Setup…
Q: Why is it so difficult to expand a service company across borders to another country? What are the…
A: There are various methods companies can take to expanding their business internationally, and each…
Q: Construct the Project Network Diagram 2.Find the Expected Duration and Standard Deviation and…
A: The critical path is a method for determining the most efficient way to complete a project. It…
Q: For each task not on the critical path, by how much could the start be delayed assuming that each…
A: Maximum possible delay in each non critical activity(activity not on the critical path) is the sum…
Q: a) Explain what a “supply chain” is. b) Explain why practioneers of supply chain management need…
A: Supply chain management is an important part of business strategy. It can be used to improve…
Q: Determine the most profitable number of each model of robot to produce during the coming month. [PX]
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Draw out the below process: Customer places an order, the order is the specified a delivery time…
A: Different steps found in the given process are listed below. Placing an order with a delivery time…
Q: Discuss the drivers and useful sources of information while moving from domestic to international…
A: Careful deliberation is required before deciding to obtain raw materials and/or components for your…
Q: If facilities have lower fixed costs a. a few high-capacity facilities are preferred because this…
A: If facilities have lower fixed costs a. a few high-capacity facilities are preferred because this…
Q: Using the centre of gravity location technique, determine the location coordinates that will…
A: Uses of the center of gravity location technique: Locating the single facilities by taking into…
Q: Create a decision table and a decision tree. b) If the executive is an optimistic decision maker,…
A: A decision tree is used to make a decision by evaluating the possible outcomes of a given event.…
Q: Data collected on the yearly registrations for a Six Sigma seminar at the Quality College are shown…
A: Given data is Alpha = 0.40 Forecast for year 1 = 5
Q: Find an example from the internet of the application of lean thinking to a service operation.…
A: "Since you have asked multiple questions, we will be answering the first question for you. If you…
Q: (3) A project was planned using PERT. Its expected completion time was determined to be 85 days. The…
A: NOTE: We are allowed to do one question only. Ans 3.
Q: Data collected on the yearly registrations for a Six Sigma seminar at the Quality College Year 1…
A: A time series forecasting technique called exponential smoothing may be expanded to handle data with…
Q: A project is scheduled to complete in six months duration. There are two activities in the project.…
A: Actual cost of Activity 1 = AC1 = SAR 300,000 Actual cost of Activity 2 = AC2 = SAR 200,000 Planned…
Q: task duration (hours) predecesor 1 predecesor 2 predecesor 3 A 4 B 5 C 3 A D 3 A…
A: Formulae used: Cycle Time = Operation time/dayoutput /day Theoretical minimum number of…
Q: In your own words, describe cost of quality (COQ) and why an organization should be managing COQ.
A: Today the business world is becoming ever more competitive day by day. The client has a broad range…
Q: Rent'R Cars is a multisite car rental company in the city. It is trying out a new "return the car to…
A: Ans) Formula:
Q: Dunstreet's Department Store would like to develop an inventory ordering policy with a 99 percent…
A: The quantity of inventory a company should always retain to run most successfully is the optimal…
Q: Questions 1.Explain using illustrations how forecasting features in this company's operations.…
A: Forecasting is a technique to predict future value. It is useful to predict future demand, sales, or…
Q: What is your forecast for next year's sales? (Do not round intermediate calculations and round your…
A: The least squares method of forecasting is based on the principle that the sum of squared errors…
Q: You are planning the new layout for the local branch of the Sixth Ninth Bank. You are considering…
A: As per the given description of the question, the following information is extracted. Number of…
Q: Under the operations analysis, how do you complete resource allocation?
A: Every company has some objectives and all the processes, strategies, and hard work is made to…
Q: I What is the bullwhip effect and how does it relate to lack of coordination in the supply chain?
A: The bullwhip effect occurs in distribution channels when supply chain inefficiencies are caused by…
Q: Define "knowledge-based systems"
A: A type of artificial intelligence (AI) known as a knowledge-based system (KBS) aims to support…
Q: e weapon" Justify the statemen
A: Since quality is an integral component of an organization's overall competitive advantage, the…
Q: Considering the Project Details; 1.Construct the Project Network Diagram 2.Find the Expected…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: terested in arriving at a forecast of rentals so that she can order the correct quantities of…
A: Ans) Formula:
Q: The success of any project is dependent on a diverse range of skills, abilities and competencies of…
A: An expert who organizes, plans, and manages projects while adhering to constraints like finances and…
Q: GRAPH METHOD Graph-Based Method: Example Lets consider the following relationship chart and using…
A: Graph based method is construction type layout method which is used with an adjency based objective…
Q: which of the following will provide the must reliable estimate of the time required for a company…
A: Too often, deadlines are missed or teams overextend themselves because the project manager failed to…
Q: ABC Wash, Inc., makes commercial and industrial laundry machines (the kinds hotels use), and has…
A: Find the Level Strategy below: a. The Cost of the strategy is $ 1380400 b. Back order Requirement:…
Q: List and describe the differences between forecasts and predictions?
A: The future is the very first thing that comes to our minds whenever we hear the words "forecasting"…
Q: XYZ Corporation operates two plants, each of which has a capacity of 170 units per day. Each day,…
A: Given that:
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
- Martha has been assigned a team of 10 people to help her plan a major customer appreciationevent. They have been working together for over a month now and they just haven’t really cometogether as a team. She was sure she started off well. She contacted each individual on the teamand let them know their responsibilities on the project. Each of the members gets the taskscompleted, but don’t seem concerned with the others on the team. If someone needs help, no onepitches in to assist. If a team member has a problem, no one helps him to solve that problem. Justyesterday one of the team members had an emergency and asked if someone on the team couldhave a call with the sales team so she could leave early. No one offered to help so Martha jumped in to assist. Martha had to do something. This was a bad experience for everyone frankly and somefolks already were talking about getting off the project. Plus she felt the event won’t be as good asit could if they just came together as a team. In…At the close of your project, you measure the customer satisfaction and findthat some customer needs were not fully met. Your supervisor asks you whatsteps you took on your project to improve customer satisfaction. Whichsubsidiary plan would you consult to determine this information?A. Communications management planB. Staffing management planC. Quality Management planD. Risk management plan Customer satisfaction should be measured at the end of the project tomaintain long-term relationships. Which of the following is NOT always anaspect of customer satisfaction?A. The product meets its stated and unstated requirementsB. The product is high qualityC. The customer’s needs are metD. The project is profitableParagraph Styles Eg Problem 2 The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Immediate Normal Time Crash Time Normal Cost Crash Cost Activity Predecessor(s) (weeks) (weeks) ($) 7,000 3,000 ($) A None 1 10,000 None 2 3,000 A 3 1 12,000 40,000 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 5,000 15,000 3 9,000 18,000 F, G 6. 14,000 32,000 Construct a network diagram for the project. a. b. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? с. d. What is the minimal total cost associated with completing the project in 16 weeks? e. What is the total time for the…
- You may need to use the appropriate technology to answer this question. The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group. The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is depicted in the following diagram. Start Activity A B с D The activity time estimates (in weeks) are listed in the following table. Optimistic Most Probable Pessimistic E F G H I J 3 3 4 2 7 6.5 4.5 6 2 A 4 B 4 3.5 5 3 10 7.5 6 F 7 E 5 2.5 D H 5 7 6 4 13 11.5 7.5 14 6 6 J Finish (a) Develop an activity schedule for this project and identify the critical path activities. (Enter your answers as a…Assume Bangladesh National Cricket Team needs to find a new head coach for the team. The cricket team’spresent and the future success largely depends on the formulations and implantation of the plans laid by thehead coach. The cricket board has given you the responsibility to prepare the job responsibilities of the newhead coach. You need to pinpoint very carefully which tasks he is supposed to do, as you also need to identifywhich skills and qualifications he must possess to do those required tasks smoothly. Prepare the job descriptionand job specification for the position of “Head Coach” of Bangladesh Cricket Team.1. Relate the project management lifecycle to the application development of a house cleaning service. 2. Identify and develop a PowerPoint presentation on what happens at each phase of the project management lifecycle of application development of a house cleaning service. 3. Ensure you cover the ket aspects such as: i.Initiating process ii. Planing process iii. Executing process iv. Monitoring and controlling process v. Closing process
- You are an electronic engineer who is working on the design, production and implementation of Digital electronic circuits for customers of an electronic company. You manager has given you two digital electronic circuits to analyze and explain their operations. You need to write a report for the manager so he can pass this on to the customers who will be using these circuits. The report should include a section for each circuit. Task 1 You manager has asked you to write a report to a customer who will be using the following digital circuits that implement combinational circuits in their operation: 1.. A one bit, 3 input majority counter (voter)Within your report, you need to explain and analyze the construction and operation of the circuit making sure the customer knows how it works in simple steps. You need to include in your report the truth table of the circuit and also need to use the Boolean Algebra/Karnaugh Map to minimize the number of gates used in the design and…You are given the following data for an activity: ES = 10 EF = 15 LS = 16 Which of the following can you determine from this data? A. The activity's float and duration B. Only the activity float C. Only the activity duration D. Neither the activity's float nor its durationEvaluate the below statement according to the project management terminologies and choose the correct answer: It is the process of making a forecast or precise approximation Choose... of time and cost associated with a work package or activity. Graphically describes a project consisting of well-defined Choose.. activities, the completion of which marks its end. One of the Perform Quantitative Risk Analysis process has a Choose.. Tools and Techniques. Useful for building accountability through assigning specific Choose.. tasks to team members. It is the standard format each path through the network must be continuous with no gaps, discontinuities, or dangling Choose... activities. Organizational Assets, Project Scope Statement, Cost Management Plan and Schedule Management Plan are inputs Choose.. of: Choose... Work Breakdown Structure Expert Judgment Bar chart Estimating A horizontal diagram format Plan Risk Management
- You are managing a large construction project that’s been broken down intosub-projects (or phases). Each of these sub-projects is scheduled to takebetween three and six months to complete. At the end of each sub-project,you plan to go through the closing processes and document lessons learned.Which of the following BEST describes what you must do at the beginning ofeach sub-project or phase?A. Develop the preliminary scope statement for the phaseB. Make sure you don’t involve the team, to avoid introducing too much projectmanagement overheadC. Use the Earned Value Technique to decide whether or not to finish the projectD. Release all resources from the project and contact sellers to renegotiate allcontractsIn Special Events and Management 1. Event Planning and Organization Choose a type of special event (e.g., fundraiser, conference, gala) anddevelop a comprehensive plan for organizing it. Identify the event's goals, target audience, timeline, and location. Develop a detailed schedule of activities and assign responsibilities toteam members. Ensure that all necessary permits, licenses, and insurance are obtained.2. Budgeting and Financial Management Develop a realistic budget for the special event. Identify all sources of revenue and expenses. Monitor expenses throughout the planning process to ensure that thebudget is not exceeded. Develop contingency plans for unexpected expenses. 3. Logistics and Operations Management Develop a detailed plan for managing logistics and operations during thespecial event. Ensure that all necessary equipment, supplies, and personnel areavailable. Coordinate with vendors, contractors, and other third-party serviceproviders as…1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?