The expected monetary value using inside engineers to complete the design is S (Enter your response as an integer)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

Give typed full explanation 

K
Sox Engineering designs and constructs air conditioning and heating (HVAC) systems for hospitals and clinics. Currently the company's staff is overloaded with design
work. There is a major design project due in 7 weeks. The penalty for completing the design late is $14,000 per week, since any delay will cause the facility to open t
later than anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all
work. Sox has estimated that it will cost $10,000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Sox is also
considering having an outside engineering firm do the design. A bid of $90,000 has been received for the completed design. Yet another option for completing the
design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of $56,000. Sox would
then complete the rest of the design and control systems at an estimated cost of $30,000. Sox has estimated the following probabilities of completing the project within
various time frames when using each of the three options. Those estimates are shown in the following table
On Time
04
0.3
0.1
Probability of Completing the Design
One Week Late
04
Option
Internal Engineers
External Engineers
Joint Design
The expected monetary value using inside engineers to complete the design is $
0.4
02
Two Weeks Late
0.2
02
0.5
Three Weeks Late
0.1
0.2
(Enter your response as an integer)
Transcribed Image Text:K Sox Engineering designs and constructs air conditioning and heating (HVAC) systems for hospitals and clinics. Currently the company's staff is overloaded with design work. There is a major design project due in 7 weeks. The penalty for completing the design late is $14,000 per week, since any delay will cause the facility to open t later than anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Sox has estimated that it will cost $10,000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Sox is also considering having an outside engineering firm do the design. A bid of $90,000 has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of $56,000. Sox would then complete the rest of the design and control systems at an estimated cost of $30,000. Sox has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following table On Time 04 0.3 0.1 Probability of Completing the Design One Week Late 04 Option Internal Engineers External Engineers Joint Design The expected monetary value using inside engineers to complete the design is $ 0.4 02 Two Weeks Late 0.2 02 0.5 Three Weeks Late 0.1 0.2 (Enter your response as an integer)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,