OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9780077835439
Author: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 12, Problem 3P

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is on” hour. Sequence” the jobs in priority order 1, 2, 3, 4.

JobWork Center/Machine Hours Due Date (days)
1 A/3, B/2, C/2 3
2 C/2, A/4 2
3 B/6, A/1, C/3 4
4 C/4, A/1, B/2  3
  1. a. What is the make span?
  2. b. How much machine idle time is there?
  3. c. When is each job delivered compared with its due date?
  4. d. How much idle time (waiting time) is there for each job?
  5. e. Devise a better job sequence for processing.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The makespan.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The makespan is 18 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  1

Construct the Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  2

Hence, the total makespan is 18 hours (refer the Gantt chart).

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The machine idle time.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The machine idle time is 24 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  3

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  4

Determine the idle time for Machine A:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(3+4+1+1)=189=9 hours

Determine the idle time for Machine B:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(2+6+2)=1810=8 hours

Determine the idle time for Machine C:

It can be determined that the subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(2+2+3+4)=1811=7 hours

Determine the machine idle time:

It can be calculated by adding the idle time of Machine A, Machine B, and Machine C.

Machine idle time=Idle time of Machine A+Idle time of Machine B+Idle time of Machine C=9+8+7=24 hours

Hence, the total machine idle time is 24 hours.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The delivery time of each job compared to due dates.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The delivery time does not exist due date.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  5

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  6

Determine the delivery time:

Due date is given in days. It must be converted to hours by considering working hours per day is 8 hours.

Job Due date (hours) Delivery time (hours)
1 24 9
2 16 7
3 32 18
4 24 14

Delivery time is taken from the Gantt chart. Example: Job 1 is on its 9th hour at last. After that there is no Job 1.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The idle time of the jobs.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The job idle time is 11 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  7

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  8

Determine the idle time of the jobs

There is no idle time for Job 1 and Job 2. However, Job 3 has the idle time of 6 hours in Machine C from 9th hour to 15th hour (Refer Gantt chart). Job 4 has the idle time of 5 hours in Machine A from 8th hour to 13th hour (Refer Gantt chart).

Hence, the total idle time is 11 hours.

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The better sequence for processing.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The makespan is 14 hours and the better sequence is 3, 2, 4, and 1.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  9

Construct the Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  10

Hence, the total makespan is 14 hours (refer the Gantt chart).

Determine the idle time for Machine A:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(3+4+1+1)=149=5 hours

Determine the idle time for Machine B:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(2+6+2)=1410=4 hours

Determine the idle time for Machine C:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(2+2+3+4)=1411=3 hours

Determine the machine idle time:

It can be calculated by adding the idle time of Machine A, Machine B, and Machine C.

Machine idle time=Idle time of Machine A+Idle time of Machine B+Idle time of Machine C=5+4+3=12 hours

Hence, the total machine idle time is 12 hours.

Determine the delivery time:

Due date is given in days. It must be converted to hours by considering the working hours per day as 8 hours.

Job Due date (hours) Delivery time (hours)
1 24 14
2 16 7
3 32 12
4 24 12

Delivery time is taken from the Gantt chart. Example: Job 2 is on its 7th hour at last. After that there is no Job 2.

Hence, the sequence 3, 2, 4, and 1 is better in makespan and idle time.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
I only need help with question 4, but question 3 explains how to do 4 but I'm lost. I already have question 3 done.   3. Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours Due Date (days) Job 1 A/3, B/2, C/2 Job 2 C/2, A/4 Job 3 B/6, A/1, C/3 Job 4 C/4, A/1, B/2 a. What is the makespan? b. How much machine idle time is there? c. When is each job delivered compared with its due date? d. How much idle time (waiting time) is there for each job? e. Devise a better job sequence for processing. 4. In problem 3, assume there are two machines of type A, two of type B, and two of type C. a. Prepare a finite capacity schedule. b. Compare the FCS to the Gantt chart in problem 3.
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job A B Processing Time (days) I5 Due Date 11 6 3 16 19 10 D E 15 Using the earliest due date (EDD) rule, the average lateness for the five jobs is decimal place. Round your answer to one Your Answer: Answer
The following jobs are waiting to be processed at JulieMorel’s machine center:JOB DATE ORDER RECEIVED PRODUCTIONDAYS NEEDED DATE ORDER DUEA 110 20 180B 120 30 200C 122 10 175D 125 16 230E 130 18 210 In what sequence would the jobs be ranked according to the fol-lowing rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are according to shop calendar days. Today on the planning cal-endar is day 130, and none of the jobs have been started or sched-uled. Which rule is best?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY