EBK OPERATIONS MANAGEMENT
EBK OPERATIONS MANAGEMENT
14th Edition
ISBN: 9781260718447
Author: Stevenson
Publisher: MCG COURSE
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 13, Problem 11P

Determine material requirements plans for pans N and V and subassembly I as described in Solved Problem 3 for each of the following:

a. Assume that there are currently 100 Ns on hand and scheduled receipts of 40 Is and 10 Vs at the beginning of week 3. No Es are on hand: 120 Es are needed at the start of week 5.

b. Assume on-hand and scheduled receipts as in part a. Now suppose that 100 Es are needed at the stmt of week 5 and 55 at the start of week 7. Also, use multiples of these order sizes: N, 800; V, 200. Use lot-for-lot ordering for I.

C. Using your answer to part b, update the MRP for V, using the following additional information for each of these cases: (1) one week has elapsed (making it the start of week 2), and (2) three weeks have elapsed (making it the start of week 4).

The updated master schedule now has an order for 100 units of E in week 9. Your plan should cover weeks 2 through 9 for case 1, and weeks 4 through 11 for case 2. Assume all orders are released and received as planned.

Blurred answer
Students have asked these similar questions
A factory has just received an order for 95 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Lead Time On Hand Scheduled Direct Item Order Policy (weeks) Inventory receipts Components End item lot for lot A(3), B(2) 2 15 10 52 at week 3 lot for lot C(5), D(3) 20 60 at week 4 lot for lot D(3) 100 min. of 500 1 12 lot for lot Develop the material requirements plan (please print out an empty MRP table to work with), and determine how many units of component D are needed in the "planned order release" Input should be an exact number.
Given the following MRP matrix for Item D, Complete the MRP matrix below to identify the projected on hand quantity at the end of period 5? Write you answer in the answer box. (Write the number only, DO NOT write the units, i.e. items, pieces, or units etc) ITEM: D Lot Size: Period POQ 2 4 5 7 120 Gross Requirements Schedule Receipts 60 90 150 150 180 270 Project on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases Page 9 of 20 Act Previous Page Next Page 36°C S.W 2020
In the following MRP planning schedule for Item J, indicate the planned order releases to meet the gross requirements. Lead time is one week and there is no inventory on hand and safety stock. WEEK NUMBER ITEM J Gross 0 1 2 3 4 5 68 45 65 requirements Scheduled Receipts Net requirements Planned order receipt Planned order release 31 ○ 40 in week 1, 50 in week 2, and 45 in week 3 O 40 in week 1, 50 in week 2, and 45 in week 3 ○ 40 in week 2, 50 in week 3, and 68 in week 4 O 37 in week 1, 45 in week 3, and 65 in week 4

Chapter 13 Solutions

EBK OPERATIONS MANAGEMENT

Ch. 13 - Prob. 7DRQCh. 13 - Briefly discuss the requirements for effective...Ch. 13 - Prob. 9DRQCh. 13 - How can the use of MRP contribute to productivity?Ch. 13 - Prob. 11DRQCh. 13 - What is lot sizing. what is its goal, and why is...Ch. 13 - Contrast planned-order receipts and scheduled...Ch. 13 - If seasonal variations are present, is their...Ch. 13 - Prob. 15DRQCh. 13 - What are some unforeseen costs of ERP?Ch. 13 - What trade-offs are involved in the decision to...Ch. 13 - Who in the organization needs to be involved in...Ch. 13 - Prob. 3TSCh. 13 - Prob. 1CTECh. 13 - Give one example of unethical behavior involving...Ch. 13 - a. Given the following diagram for a product,...Ch. 13 - Prob. 2PCh. 13 - Prob. 3PCh. 13 - Eighty units of end item E are needed at the...Ch. 13 - a. One hundred twenty units of end item Z are...Ch. 13 - A table is assembled using three components, as...Ch. 13 - Eighty units of end item X are needed at the...Ch. 13 - Oh No!, Inc., sells three models of radar detector...Ch. 13 - Assume that you are the manager of a shop that...Ch. 13 - Assume that you are the manager of Assembly, Inc....Ch. 13 - Determine material requirements plans for pans N...Ch. 13 - A firm that produces electric golf carts has just...Ch. 13 - Refer to Problem 12. Assume that unusually mild...Ch. 13 - Using the accompanying diagram, do the following:...Ch. 13 - A company that manufactures paving material for...Ch. 13 - Prob. 16PCh. 13 - The MRP Department has a problem. Its computer...Ch. 13 - Develop a material requirements plan for component...Ch. 13 - How many wheels sets should the manager order?Ch. 13 - When should the wheel sets be ordered?Ch. 13 - Prob. 2.1CQCh. 13 - Prob. 1OTQCh. 13 - Prob. 2OTQCh. 13 - Suppose the company has just received an order for...Ch. 13 - Prob. 4OTQCh. 13 - Prob. 5OTQ

Additional Business Textbook Solutions

Find more solutions based on key concepts
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...

Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)

2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)

2. Identify four people who have contributed to the theory and techniques of operations management.

Operations Management: Sustainability and Supply Chain Management (12th Edition)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY