Assume that you are the manager of a shop that assembles power tools. You have just received an order for 50 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows:
a. Develop a product structure tree, an assembly time chart, and a master
b. Develop the material requirements plan for component E using lot-for-lot ordering for all items.
Want to see the full answer?
Check out a sample textbook solutionChapter 13 Solutions
EBK OPERATIONS MANAGEMENT
Additional Business Textbook Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Operations Management, Binder Ready Version: An Integrated Approach
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Business in Action
- Given the following product structure, master production schedule, and inventory status below and assuming the requirements for each BOM item is 1: (a) develop a gross requirements plan for Item C; (b) develop a net requirements plan for Item C. Click the icon to view the product structure, master production schedule and inventory status. a) Develop a gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents: items A and H. (Enter your responses as whole numbers). Item A Gross req 1 2 More Info 3 Period Gross requirements: A Gross requirements: H Item A B C D E 4 A On Hand 15 110 60 40 85 5 Week 6 7 8 100 Lead Time 1 2 2 1 2 Q 9 90 8 Item F G H E J K 10 60 9 On Hand 80 65 20 110 110 10 11 50 E H K 11 12 12 160 Lead Time 2 1 1 2 2 G C ■ G Xarrow_forwardThe following table lists the components needed to assemble an end item. Assume there is no on-hand inventories. Item Direct Components End item A(4), B(5), C(4) A E(3), F(2) B D(3), E(5) C F(4) D E F E(4) If 3 units of the end item are to be assembled, how many units of component E are needed? Input should be an exact number.arrow_forwardProduct M is made of two units of N and two of P. N is made of two units of R and four units of S. R is made of one unit of S and three units of T. P is made of two units of T and four units of U. a. Show the bill-of-materials (product structure tree). b. If 100 Ms are required, how many units of each component are needed? c. Show both a single-level parts list and an indented parts list.arrow_forward
- Given the product structure, master productionschedule, and inventory status in Figure 14.13, and assuming therequirements for each BOM item is I:a) develop a gross requirements plan for Item C;b) develop a net requirements plan for Item C.arrow_forwardDevelop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forwardYou need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. a) Complete the product structure. Alpha D(2) D(3)arrow_forward
- Consider the bill of materials (BOM) in Figure 11.33.a. How many immediate parents (one level above) does item I have? How many immediate parents does item E have?b. How many unique components does product A have at all levels?c. Which of the components are purchased items?d. How many intermediate items does product A have at all levels?e. Given the lead times (LT) in weeks noted on Figure 11.33, how far in advance of shipment must a purchase commitment be for any of the purchased items identified in part (c)?arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. A. Design a product structure noting the quantities for each item and show the low-level coding. B. Determine the gross quantities needed of each item if you are to assemble 50 brackets. C. Compute the net quantities if there are 25 of the base and 100 of the clamp in stock.arrow_forward1-Develop the production schedule for each component in parent item A.Make sure the independent demand for B and C are also included in theschedule.arrow_forward
- a. Write the product structure diagram as an indented bill-of-materials list.arrow_forwarda. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z,70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units ofcomponent C in week 4. Lead times are two weeks for Z and B, and one week for the other components. Lot-for-lot ordering will be used for all items b. Ninety-five units of end item E are needed at the beginning of week 7. Prepare a material requirements plan for component D. Take into account that 5 units of E are currently on hand, as well as50 units of B, 100 units of C, and 80 units of D. Also, 30 units of C have been outsourced and areexpected to arrive in week 4. Lead times are two weeks for E and C, and one week for the othercomponents. Assume lot-for-lot ordering except for D, where multiples of 40 must be used.arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F (enter your responses as whole numbers).arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.