Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
expand_more
expand_more
format_list_bulleted
Question
Chapter 12, Problem 2.1Q
Summary Introduction
To find:The duration that T technologies will spend on building B model this year and when the company will start working on it.
Introduction:Companies can produce different models of a product at a time. In this type of production, companies need to set batches for doing production in an economical way. The method in which schedules are prepared for the production of mixed models is known as mixed-model
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
TRUE/FALSE Henry Ford's introduction of the Model "T" was the first example of mass customization.
A-Plus Printing
Setup fee: $20
Each poster: $0.10
Print More
Setup fee: $55
Each poster: $0.05
Complete the table to see how much it would cost for different numbers of posters. After completing the table, what do you notice?
the table is in the image
What is level scheduling? What is the basic philosophyunderlying it?
Chapter 12 Solutions
Practical Operations Management
Ch. 12 - Prob. 1DQCh. 12 - Prob. 2DQCh. 12 - Prob. 3DQCh. 12 - Prob. 4DQCh. 12 - Prob. 5DQCh. 12 - Prob. 6DQCh. 12 - Prob. 1PCh. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Prob. 4P
Ch. 12 - Prob. 5PCh. 12 - Prob. 6PCh. 12 - Prob. 7PCh. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Prob. 10PCh. 12 - Prob. 11PCh. 12 - Prob. 12PCh. 12 - Prob. 13PCh. 12 - Prob. 14PCh. 12 - Prob. 15PCh. 12 - Prob. 16PCh. 12 - Prob. 17PCh. 12 - Prob. 18PCh. 12 - Prob. 19PCh. 12 - Prob. 20PCh. 12 - Prob. 21PCh. 12 - Prob. 22PCh. 12 - Prob. 23PCh. 12 - Prob. 24PCh. 12 - Prob. 25PCh. 12 - Prob. 26PCh. 12 - Prob. 27PCh. 12 - Prob. 1.1QCh. 12 - Prob. 1.2QCh. 12 - Prob. 1.3QCh. 12 - Prob. 1.4QCh. 12 - Prob. 2.1QCh. 12 - Prob. 2.2QCh. 12 - Prob. 2.3QCh. 12 - Prob. 3.1QCh. 12 - Prob. 3.2QCh. 12 - Prob. 3.3Q
Knowledge Booster
Similar questions
- What technology choice is appropriate for lockout/tagout in the context of service or maintenance activities?arrow_forwardProduct A Order Qty = 400 Order Lead Time = 2 Forecast Demand Scheduled Receipts Projected Available Inventory 400 Planned Order Receipts Planned Order Releases 1 300 OD 4, 6, 2 300 400 Sketch and fill in the grid on scrap paper to use on upcoming questions In what periods would you incur a planned order release? OA 1.3, and 4 2.4, and 5 OC 3,5, and 6 and 7 3 300 PERIODS 4 300 5 300 6 300 7 100 8 100arrow_forwardRefer to Figure 11.23 and Solved Problem 1. If inventory consists of two units of B, one unit of F. and three units of G, how many units of G. E. and D must be purchased to produce five units of product A? Figure 11.23 for Product A D(1) LT-3 B(3) LT-2 EG LT-6 FIT) CO) LT-1 GALA LT=3 D(1) LT-3 LT-Lead timearrow_forward
- How many production runs of wheel bearings that will be in have in a year?arrow_forwardTable B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B). Table A Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7 Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B Item: Ball bearings Quantity on hand: 400 Order policy: 500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory MPS quantity 500 MPS start Available to promise (ATP)arrow_forwardIn the case of any ERP system, what is the ideal testing strategy?arrow_forward
- Demand for the popular water toy Sudsy Soaker has far exceeded expectations. In order to increase the availability ofdifferent models of the toy, the manufacturer has decided tobegin producing its most popular models as often as possible on its one assembly line. Given monthly requirementsof 7200, 3600, and 3600 units for Sudsy Soaker 50, SudsySoaker 100, and Sudsy Soaker 200, respectively, determinea model sequence for the final assembly line that willsmooth out the production of each model. (Assume 30working days per month and eight working hours per day.Also assume that the time required to assemble each modelis approximately the same.)arrow_forwardHow much will they save in annual setup costs with this new lower production quantity?arrow_forwardDraw a simple bill-of-materials (BOM) for a smart phone given the following requirements: (a) clearly label the end item and each component, (b) the BOM must contain no more than ten items, (c) the BOM must contain at least three levels (you may count the end-item level zero).arrow_forward
- Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 4,500 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 8,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 3,500 Week 1 2 3 Gross requirements 4,500 1,000…arrow_forwardBased on the following product structure figure. A thousCnd and five hundred units of product A are needed to produCe. How many units of B, C, D, E, and F are needed and determine all the units level (low level code)? B(1) C (2) D (2) E (1) D (1) F (1) F (4) Low Level Code Unit Quantityarrow_forwardYear Demand History for the Bow Rake: DEMAND Month Year 1 Year 2 Year 3 Year 4 1 55,220 39,875 32,180 62,377 2 57,350 64,128 38,600 66,501 3 15,445 47,653 25,020 31,404 4 27,776 43,050 51,300 36,504 5 21,408 39,359 31,790 16,888 6 17,118 10,317 32,100 18,909 7 18,028 45,194 59,832 35,500 8 19,883 46,530 30,740 51,250 9 15,796 22,105 47,800 34,443 Prepare a graph that shows the four-year demand history for the bow rake. Discuss any apparent trend and seasonal patterns. 2. Which forecasting method might be best for bow rakes for each month of Year 5? Why?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.