Question
Chapter 12, Problem 6P
Summary Introduction
Interpretation: Permission granted by second type of card is to be determined.
Concept Introduction: Kanban:
Since inventories are located in several locations in a large production unit; it will be very difficult to track the inventories. Proper monitoring of the bins is essential. Kanban system uses different cards to signal and regulate the production of a plant.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Flores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.
Setup cost
$16
Annual holding cost subassembly $250 per subassembly
600 subassemblies
Daily production
Annual usage
62,500 (-50 weeks x5 days each x daily usage of 250
subassemblies)
Lead time
Safety stock
The kanban size is (round your response to the nearest whole number).
2 days
1 day's production of subassemblies
Krupp Refrigeration, Inc., is trying to reduce inventory and wants you to install a kanban system for compressors on one of itsassembly lines. Determine the size of the kanban and the number of kanbans (containers) needed.Setup cost = $10Annual holding cost per compressor = $100Daily production = 200 compressorsAnnual usage = 25,000 (50 weeks * 5 days each * daily usage of 100 compressors)Lead time = 3 daysSafety stock = 1
2 day’s production of compressors
The required number of kanbans equals:a) I.b) Demand during lead time I Qc) Size of container.d) Demand d uring lead time.e) Demand during lead time+ Safety stock I Size of container
Chapter 12 Solutions
Practical Operations Management
Ch. 12 - Prob. 1DQCh. 12 - Prob. 2DQCh. 12 - Prob. 3DQCh. 12 - Prob. 4DQCh. 12 - Prob. 5DQCh. 12 - Prob. 6DQCh. 12 - Prob. 1PCh. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Prob. 4P
Ch. 12 - Prob. 5PCh. 12 - Prob. 6PCh. 12 - Prob. 7PCh. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Prob. 10PCh. 12 - Prob. 11PCh. 12 - Prob. 12PCh. 12 - Prob. 13PCh. 12 - Prob. 14PCh. 12 - Prob. 15PCh. 12 - Prob. 16PCh. 12 - Prob. 17PCh. 12 - Prob. 18PCh. 12 - Prob. 19PCh. 12 - Prob. 20PCh. 12 - Prob. 21PCh. 12 - Prob. 22PCh. 12 - Prob. 23PCh. 12 - Prob. 24PCh. 12 - Prob. 25PCh. 12 - Prob. 26PCh. 12 - Prob. 27PCh. 12 - Prob. 1.1QCh. 12 - Prob. 1.2QCh. 12 - Prob. 1.3QCh. 12 - Prob. 1.4QCh. 12 - Prob. 2.1QCh. 12 - Prob. 2.2QCh. 12 - Prob. 2.3QCh. 12 - Prob. 3.1QCh. 12 - Prob. 3.2QCh. 12 - Prob. 3.3Q
Knowledge Booster
Similar questions
- Please do not give solution in image formate thanku. Markland First National Bank of Rolla utilizes kanban techniques in its check processing facility. The following information is known about the process. Each kanban container can hold 50 checks and spends 48 minutes a day in processing and 4 hours a day in materials handling and waiting. Finally, the facility operates 24 hours per day and utilizes a policy variable for unforeseen contingencies of 0.20. a. If there are 43 kanban containers in use, the current daily demand of the check processing facility is ______units.arrow_forwardIn which ways, if any, are the following systems analogous to kanban: returning empty bottles to the supermarket and picking up filled ones; running a hot dog stand at lunchtime; withdrawing money from a checking account; raking leaves into bags?arrow_forwardIn which ways, if any, are the following systems analogous to kanban: returning empty bottles to the supermarket and picking up filled ones; running a hot dog stand at lunch- time; withdrawing money from a checking account; raking leaves into bags?arrow_forward
- Tej Dhakar’s company wants to establish kanbans tofeed a newly established work cell. The following data have beenprovided. How many kanbans are needed?Daily demand 250 unitsLead time 12 daySafety stock 14 dayKanban size 50 unitsarrow_forwardIn which ways, if any, are the following systems analogous to kanban: returning empty bottles to the supermarket and picking up i lled ones; running a hot dog stand at lunchtime; withdrawing money from a checking account; raking leaves into bags?arrow_forwardConsider that a production company uses dual-card Kanban system. How can this company gradually reduce the total number of inventories using Kanban system? Note that the company must continue using Kanban system. Please make sure that you explain the process and logically explain how can the company reduce inventories using Kanban.arrow_forward
- WHAT IS A KANO MODELarrow_forwardA manufacturer of instrument gauge clusters (gauges) uses a Kanban system to control material flow. The gauges are transported in a container that holds four. The demand at a downstream fabrication center is approximately 12 gauges per hour. It takes approximately three hours for the gauges to be replenished by an upstream work center. Due to variations in fabrication times, management has decided to keep 2 percent of the needed inventory as safety stock. Given the data above, how many Kanban cards are required? Please round your answer to the nearest whole number.arrow_forwardThe production schedule at Mazda calls for 1,200 Mazdas to be produced during each of 22 production days in January and 900 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from Gesundheit. The safety stock policy variable, α, is 0.15. The container (a delivery truck) size is 200 tires. The average waiting time plus materials handling time is 0.16 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing time per container in January is 0.10 day. February processing time will average 0.125 day per container. How many containers should be authorized for January?How many for February?arrow_forward
- Hartley Electronics, Inc., in Nashville, producesshort runs of custom airwave scanners for the defense industry. The owner, Janet Hartley, has asked you to reduce inventory by introducing a kanban system. After several hours ofanalysis, you develop the following data for scanner connectors used in one work cell. How many kanbans do you needfor this connector?arrow_forwardThe production schedule at Mazda calls for 1,200 Mazdas to be produced during each of 22 production days in January and 900 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from Gesundheit. The safety stock policy variable, a, is 0.15. The container (a delivery truck) size is 200 tires. The average waiting time plus materials handling time is 0.16 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing time per container in January is 0.10 day. February processing time will average 0.125 day per container. How many containers should be authorized for January? How many for February?arrow_forwardPauline Found Manufacturing, Inc., is moving tokanbans to support its telephone switching-board assemblylines. Determine the size of the kanban for subassemblies and thenumber of kanbans needed.Setup cost = $30 Annual holding cost = $120 per subassemblyDaily production = 20 subassembliesAnnual usage = 2,500 (50 weeks * 5 days each* daily usage of 10 subassemblies)Lead time = 16 daysSafety stock = 4 days> production of subassembliesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.