Chapter 12, Problem 3.1Q
Summary Introduction
To find:The number of railcars to be placed in two-unit trains so that a thin but sufficientsupply of coal between the mine and plant can be maintained.
Introduction:The production system of every company or organization must ensure that an adequate flow of inventory is maintained. The flow of inventory is managed by reorder point systems where the inventory levels are monitored so that when the stock drops to a certain minimum point, said as reorder point, the next stock can be made ready.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A company using a kanban system has an inefficient machine group. For example, the daily
demand for part L105A is 3,000 units. The average waiting time for a container of parts is 0.8
day. The processing time for a container of L105A is 0.2 day, and a container holds 280 units.
Currently, 29 containers are used for this item.What is the total planned inventory (WIP and
finished) for L105A?
8120 units
5400 units
5410 units
8102 units
The wheat harvesting season in the American Midwest is short, and farmers deliver their truckloads of wheat to a giant central storage bin within a 2-week span. Because of this, wheat-filled trucks waiting to unload and return to the fields have been known to back up for a block at the receiving bin. The central bin is owned cooperatively, and it is to every farmer's benefit to make the unloading/storage process as efficient as possible. The cost of grain deterioration caused by unloading delays and the cost of truck rental and idle driver time are significant concerns to the cooperative members. Although farmers have difficulty quantifying crop damage, it is easy to assign a waiting and unloading cost for truck and driver of $17 per hour. During the 2-week harvest season, the storage bin is open and operated 16 hours per day, 7 days per week, and can unload 34 trucks per hour according to a negative exponential distribution. Full trucks arrive all day long (during the…
The wheat harvesting season in the American Midwest is short, and farmers deliver their truckloads of wheat to
a giant central storage bin within a 2-week span. Because of this, wheat-filled trucks waiting to unload and
return to the fields have been known to back up for a block at the receiving bin. The central bin is owned cooperatively,
and it is to every farmer’s benefit to make the unloading/storage process as efficient as possible. The
cost of grain deterioration caused by unloading delays and the cost of truck rental and idle driver time are significant
concerns to the cooperative members. Although farmers have difficulty quantifying crop damage, it is
easy to assign a waiting and unloading cost for truck and driver of $18 per hour. During the 2-week harvest season,
the storage bin is open and operated 16 hours per day, 7 days per week, and can unload 35 trucks per hour
according to an exponential distribution. Full trucks arrive all day long (during the hours the bin is open)…
Chapter 12 Solutions
Practical Operations Management
Ch. 12 - Prob. 1DQCh. 12 - Prob. 2DQCh. 12 - Prob. 3DQCh. 12 - Prob. 4DQCh. 12 - Prob. 5DQCh. 12 - Prob. 6DQCh. 12 - Prob. 1PCh. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Prob. 4P
Ch. 12 - Prob. 5PCh. 12 - Prob. 6PCh. 12 - Prob. 7PCh. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Prob. 10PCh. 12 - Prob. 11PCh. 12 - Prob. 12PCh. 12 - Prob. 13PCh. 12 - Prob. 14PCh. 12 - Prob. 15PCh. 12 - Prob. 16PCh. 12 - Prob. 17PCh. 12 - Prob. 18PCh. 12 - Prob. 19PCh. 12 - Prob. 20PCh. 12 - Prob. 21PCh. 12 - Prob. 22PCh. 12 - Prob. 23PCh. 12 - Prob. 24PCh. 12 - Prob. 25PCh. 12 - Prob. 26PCh. 12 - Prob. 27PCh. 12 - Prob. 1.1QCh. 12 - Prob. 1.2QCh. 12 - Prob. 1.3QCh. 12 - Prob. 1.4QCh. 12 - Prob. 2.1QCh. 12 - Prob. 2.2QCh. 12 - Prob. 2.3QCh. 12 - Prob. 3.1QCh. 12 - Prob. 3.2QCh. 12 - Prob. 3.3Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The wheat harvesting season in the American Midwest is short, and most farmers deliver their truckloads of wheat to a giant central storage bin within a two-week span. Because of this, wheat-filled trucks waiting to unload and return to the fields have been known to back up for a block at the receiving bin. The central bin is owned cooperatively, and it is to every farmer’s benefit to make the unloading/storage process as efficient as possible. The cost of grain deterioration caused by unloading delays, the cost of truck rental, and idle driver time are significant concerns to the cooperative members. Although farmers have difficulty quantifying crop damage, it is easy to assign a waiting and unloading cost for truck and driver of $18 per hour. The storage bin is open and operated 16 hours per day, 7 days per week, during the harvest season and is capable of unloading 35 trucks per hour according to an exponential distribution. Full trucks arrive all day long (during the hours the bin…arrow_forwardMarkland First National Bank of Rolla utilizes kanban techniques in its check processing facility. The following information is known about the process. Each kanban container can hold 50 checks and spends 24 minutes a day in processing and 2 hours a day in materials handling and waiting. Finally, the facility operates 24 hours per day and utilizes a policy variable for unforeseen contingencies of 0.25.a. If there are 20 kanban containers in use, what is the current daily demand of the check processing facility?b. If the muda or the waste in the system were eliminated completely, how many containers would then be needed?arrow_forwardA company using a kanban system has an inefficient machine group. For example, the daily demand for part L105A is 3,000 units. The average waiting time for a container of parts is 0.8 day. The processing time for a container of L105A is 0.2 day, and a container holds 270 units. Currently, 20 containers are used for this item. a. What is the value of the policy variable, α? b. What is the total planned inventory (work-in-process and finished goods) for item L105A? c. Suppose that the policy variable, α, was 0. How many containers would be needed now? What is the effect of the policy variable in this example?arrow_forward
- Markland First National Bank of Rolla utilizes kanban techniques in its check processing facility. The following information is known about the process. Each kanban container can hold 25 checks and spends 24 minutes a day in processing and 2 hours a day in materials handling and waiting. Finally, the facility operates 24 hours per day and utilizes a policy variable for unforeseen contingencies of 0.20. a. If there are 29 kanban containers in use, the current daily demand of the check processing facility is units. (Enter your response rounded to the nearest whole number.)arrow_forwardMarkland First National Bank of Rolla utilizes kanban techniques in its check processing facility. The following information is known about the process. Each kanban container can hold 25 checks and spends 24 minutes a day in processing and 2 hours a day in materials handling and waiting. Finally, the facility operates 24 hours per day and utilizes a policy variable for unforeseen contingencies of 0.20. a. If there are 29 kanban containers in use, the current daily demand of the check processing facility is 6,000 units. (Enter your response rounded to the nearest whole number.) b. If the muda or the waste in the system were eliminated completely, whole number.) containers would then be needed. (Enter your response rounded up to the nextarrow_forwardGestalt, Inc. uses a kanban system in its automobile production facility in Germany. This facility operates 8 hours per day to produce the Jitterbug, a replacement for the obsolete but immensely popular Jitney Beetle. Suppose that a certain part requires 150 seconds of processing at machine cell 33B and a container of parts average 1.6 hours of waiting time there. Management allows a 10 percent buffer for unexpected occurrences. Each container holds 30 parts, and 8 containers are authorized. How much daily demand can be satisfied with this system?arrow_forward
- Gestalt, Inc. uses a kanban system in its automobile production facility in Germany. This facility operates 8 hours per day to produce the Jitterbug, a replacement for the obsolete but immensely popular Jitney Beetle. Suppose that a certain part requires 150 seconds of processing at machine cell 33B and a container of parts average 1.6 hours of waiting time there. Management allows a 10 percent buffer for unexpected occurrences. Each container holds 30 parts, and 8 containers are authorized. How much daily demand can be satisfied with this system? (Hint: Recall that r is the average processing time per container, not per individual part.)arrow_forwardPrince Shop. owns and operates a chain of popular coffee stands that serve over 30 different coffee-based beverages. The constraint at the coffee stands is the amount of time required to fill an order, which can be considerable for the more complex beverages. Sales are often lost because customers leave after seeing a long waiting line to place an order. Careful analysis of the company's existing products has revealed that the opportunity cost of order- filling time is P34.00 per minute. The company is considering introducing a cappuccino, to be made with almond extract and double-fine sugar. The variable cost of the' standard size amaretto cappuccino would he P4 60 and new product, amarettoarrow_forwardGestalt, Inc. uses a kanban system in its automobile production facility in Germany. This facility operates 10 hours per day to produce the Jitterbug, a replacement for the obsolete but immensely popular Jitney Beetle. Suppose that a certain part requires 60 seconds of processing at machine cell 33B and an average container of parts averages 1.4 hours of waiting time there. Management has allowed a 12 percent buffer for unexpected occurrences. Each container holds 27 parts, and 5 containers are authorized. How much daily demand can be satisfied with this system? (Hint: Recall that p is the average processing time per container, not per individual part.) The average processing time per container of parts, p, is 0.045 day. (Enter your response rounded to three decimal places.) The average waiting time per container of parts, w, is day. (Enter your response rounded to two decimal places.)arrow_forward
- Gestalt, Inc. uses a kanban system in its automobile production facility in Germany. This facility operates 8 hours per day to produce the Jitterbug, a replacement for the obsolete but immensely popular Jitney Beetle. Suppose that a certain part requires 150 seconds of processing at machine cell 33B and an average container of parts averages 1.6 hours of waiting time there. Management has allowed a 10 percent buffer for unexpected occurrences. Each container holds 30 parts, and 8 containers are authorized. How much daily demand can be satisfied with this system? (Hint: Recall that p is the average processing time per container, not per individual part.) day. (Enter your The average processing time per container of parts, p, is response rounded to three decimal places.)arrow_forwardThe process of designing the multichannel system consists of five consecutive steps. Select one: a. False b. Truearrow_forwardA heat tempering machine tempers a surgical instrument in exactly 2 minutes. Surgical instruments arrive at the rate of 20 units per hour. The machine has a capacity to temper only 1 instrument at a time and there is not setup required between two tempering processes. Find the average number of surgical waiting to be tempered including the one that is going under treatment process. (A)0.33 (B) 1.33 (C) 2.33 (D) 3.33arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.